More framing was completed, the masonry work on the tower was finished, work was done on the handicap ramp for heating the ramp and keeping it ice free in the winter, Tim and Andy worked on the phone lines…
The Cry Room window is in! Concrete work was done downstairs and installation of mechanical (heating and cooling) and electrical systems are underway. New telephone and network cables will be installed soon which is work done “by owner.” Andy…
Just Builders is working on reconfiguration of our HVAC (heating and cooling) system and on the vent hoods for the new kitchen. Once these mechanical systems are complete, electricians from Goodman heating systems will be on site to install…
More brick went up on the tower — it’s almost done! Framing continues in the upstairs office area. Work continues downstairs in the kitchen and bath areas. It’s exciting to see all the changes! Thank God for this great…
Work continues. Brick is going up on the outside, walls are coming down on the inside, Xcel hooked up the gas line, so we now have a furnace, and work continues on the handicap ramp. Mark will let us…
Check out this link http://vimeo.com/30562493 to see the last four months’ worth of construction in less than 3 minutes! Thank you, Justin Le Vett, for putting this together!
Brick work continued this week, the handicap ramp was started and more contractors were here doing their work. In this next week, new electrical service will be on Monday, more work on the handicap ramp, HVAC and mechanical contractors…
On the outside of our new addition, you will see windows, waterproofing, and bricks. On the inside, framing in the new addition is well underway. Concrete in the basement floor has been opened up to place required drain lines. …
This past week, framing continued and the nursery wall was taken down and sink taken out. New framing also occurred in the nursery. Some masonry work began this week as well. This week framing the basement walls will continue…
Our addition on the east end of the church building is taking shape. Framing of the main floor is underway, and will continue next week. On the lower level, demolition of the east basement wall is complete so that…