Similar Posts
Construction Time Lapse Update
ByAWCCCheck out the latest time lapse of construction at AWCC from July through December! http://vimeo.com/34589050
Construction Update Week of December 11
ByAWCCPainting was done, the installation of the rail for the handicap ramp started, tile work began in the bathrooms, new doors were installed, and more electrical work was completed!
Work Has Started on the Parking Lot
ByAWCCIt’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…
Parking Lot Goal Reached!
ByAWCCPRAISE GOD And THANK YOU AWCC FAMILY The Parking Lot project is nearly complete and as of June 2nd, sufficient funds have been contributed to provide for the dumpster enclosure and pay off our loan in full! Thanks to all who have worked so hard and contributed generously to make our new parking lot possible….
Construction Update Week of October 9
ByAWCCWork continues. Brick is going up on the outside, walls are coming down on the inside, Xcel hooked up the gas line, so we now have a furnace, and work continues on the handicap ramp. Mark will let us know when it is safe to look around downstairs, so until then, please stay out of…
Construction Update Week of March 25
ByAWCCThere was a lot accomplished this week! Sheet rock was installed in the preschool room and the new lobby and stairway, the cement was poured for part of the new entrance; the new front doors were installed; lots of excavation happened; stucco installation began; and work on the lift continued.


