Similar Posts
Construction in Less Than Three Minutes
ByAWCCCheck out this link http://vimeo.com/30562493 to see the last four months’ worth of construction in less than 3 minutes! Thank you, Justin Le Vett, for putting this together!
November 27 Construction Update
ByAWCCInspections were completed this week. Installation was installed and drywall was delivered and installed. If you’d like to take a look around the new addition, upstairs and downstairs, it is now safe for you to do that! It’s exciting to see the progress that’s happening. Keep praying for Mark and his team.
Building Team Update
ByAWCCWhile we have not yet started construction on Phase I, we are making progress toward that goal. We are working trough details of our contract with Just Builders, checking insurance coverage for both parties, and setting up an escrow account with National Covenant Properties from which construction payments will be made. We don’t have a…
Construction Update Week of March 25
ByAWCCThere was a lot accomplished this week! Sheet rock was installed in the preschool room and the new lobby and stairway, the cement was poured for part of the new entrance; the new front doors were installed; lots of excavation happened; stucco installation began; and work on the lift continued.
Construction Update Week of October 9
ByAWCCWork continues. Brick is going up on the outside, walls are coming down on the inside, Xcel hooked up the gas line, so we now have a furnace, and work continues on the handicap ramp. Mark will let us know when it is safe to look around downstairs, so until then, please stay out of…
Phase I — Building Informational Meeting
ByAWCCWant to know more about the Building Plans? Check out the bulletin board in the lobby to review the plans, and then stay for the meeting after worship on May 8th!!


