| |

Construction Update Week of June 24

 

Landscaping was done last week, and finishing touches were worked on inside the building! Construction is almost complete!

 

 

Similar Posts

  • | |

    Construction Update Week of September 18

    This past week, framing continued and the nursery wall  was taken down and sink taken out. New framing also occurred in the nursery. Some masonry work began this week as well. This week framing the basement walls will continue and the plumbers and mechanical contractors are scheduled to come and begin work!

  • |

    Community Garage Sale

    AWCC will be hosting a community garage sale on Saturday, July 6.  Anyone interested is welcome to bring their own items to sell and is free to use their own profits at their discretion.  Each individual or family is responsible for their own set up and take down, as well as for the sale of…

  • |

    Building Update July 10

    Construction has begun! The handicap ramp is removed. All the lumber from that is going to be repurposed ! The front sidewalk has been removed and progress is being made!  We anticipate having a handicap ramp next Sunday. For safety, please do not enter the construction zone!    

  • | |

    Construction Update

    Building Update for the week of July 10-16: Excavation for Phase I construction is complete. Next up is pouring new concrete foundations.To make room for this work, the air conditioning unit and our water supply had to be relocated.  Both services have been restored and are available. On Sunday mornings, both building entrances facing the…

  • | |

    Building Team Update

    Recent progress by the Building Team towards our Phase 1 building expansion includes: Lee Architects completed a full drawing set which was submitted to Jefferson County for “plan review” on March 18. Jeffco completed their review and issued our building permit on April 1! The team has completed interviews of 4 candidates for general contractor…