$234,900.41 has been given to the Building Fund from 10/1/2010 through 1/1/2012!! That’s more than 100% of the pledged amount of $233,581.11 and 94% of the $250,000 goal. Praise God!
$234,900.41 has been given to the Building Fund from 10/1/2010 through 1/1/2012!! That’s more than 100% of the pledged amount of $233,581.11 and 94% of the $250,000 goal. Praise God!
This past week, Just Builders, began framing the new east addition. This next week they will continue framing and will also break through the old foundation walls into the lower level of the building. This begins the process of merging the new addition with the existing building. Be sure to check out the “color board”…
Beginning next Sunday, kids will remain in the service for the whole time. They will not be dismissed downstairs to KidsCrossing! The only part of the basement that will be accessible during this next phase will be the bathrooms! We need your help in making this work on Sunday mornings! If you do not have…
Our addition on the east end of the church building is taking shape. Framing of the main floor is underway, and will continue next week. On the lower level, demolition of the east basement wall is complete so that the kitchen and mechanical room now open into the new addition. (Sorry, no tours just yet.)…
Lots of demolition has occurred in the basement! Walls have come down, and new walls have been framed. Electrical work continues to happen and the staff is getting settled in their new offices. Please do not use the back stairs. You can also start using the new restrooms next Sunday!
This past week, framing continued and the nursery wall was taken down and sink taken out. New framing also occurred in the nursery. Some masonry work began this week as well. This week framing the basement walls will continue and the plumbers and mechanical contractors are scheduled to come and begin work!
Construction in the basement continues — electrical, framing, insulation, finishing the restrooms and more! Please use the new restrooms beginning today!
Brick work continued this week, the handicap ramp was started and more contractors were here doing their work. In this next week, new electrical service will be on Monday, more work on the handicap ramp, HVAC and mechanical contractors will continue their work, and the east wall between the sanctuary and the new addition will…
More insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!
The Preschool Room looks awesome, the brick work looks great. Just waiting for the manufacturer to deliver the glass for the entry way and some inspections. It’s getting close to being completed!
Our website uses cookies to improve your experience on our site. By using the site, you consent to cookies.
Websites store cookies to enhance functionality and personalise your experience. You can manage your preferences, but blocking some cookies may impact site performance and services.
Essential cookies enable basic functions and are necessary for the proper function of the website.
These cookies are used for managing login functionality on this website.
You can find more information in our Cookie Policy and .