Similar Posts
Construction Update Week of March 25
ByAWCCThere was a lot accomplished this week! Sheet rock was installed in the preschool room and the new lobby and stairway, the cement was poured for part of the new entrance; the new front doors were installed; lots of excavation happened; stucco installation began; and work on the lift continued.
Construction Update Week of April 1
ByAWCCThere was a lot accomplished again this week! The coils for the heated sidewalks were laid, concrete was poured, stucco work was down outside, more glass was installed in the new entry, and a team moved into the kitchen!
Community Garden Work Day
ByAWCCCan you come help our neighbors put the community garden to bed? Join us Saturday, October 29th (Date Change!) from 9:30 am to noon or so Bring a brunch-type finger food to share, gloves, and a water bottle. Come for all of it or just an hour. Come for any length of time!
Building Update — Week of August 14
ByAWCCThe past week the plumbing around the tower was completed and backfilled. You can see the beginnings of the tower out front. Electrical work continues. This next week the new sewer line will be trenched to the street. It will run from the new east addition, around the north side of the building, then west…
Construction Update Week of April 29
ByAWCCBrick work began on the front entrance and the pillars, the sidewalk heating system was completed, and work continued in the preschool room!
Grand Re-Opening
ByAWCCMark your calendars for Sunday, September 9th! It will be our Launch Sunday for the new year, as well as a Grand-Re-Opening , celebrating the completion of construction! We need 3-4 strong men to come on Saturday, September 8th, 8 am, to set up the tents for the celebration the next day. We also need…


