ByAWCCJust Builders is working on reconfiguration of our HVAC (heating and cooling) system and on the vent hoods for the new kitchen. Once these mechanical systems are complete, electricians from Goodman heating systems will be on site to install new electrical circuits. New telephone and network cables will be installed soon which is work done…
Building Update — Week of August 14
ByAWCCThe past week the plumbing around the tower was completed and backfilled. You can see the beginnings of the tower out front. Electrical work continues. This next week the new sewer line will be trenched to the street. It will run from the new east addition, around the north side of the building, then west…
Construction Update August 7
ByAWCCThe week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…
Construction Update Week of September 18
ByAWCCThis past week, framing continued and the nursery wall was taken down and sink taken out. New framing also occurred in the nursery. Some masonry work began this week as well. This week framing the basement walls will continue and the plumbers and mechanical contractors are scheduled to come and begin work!
Construction Update Week of February 12
ByAWCCDry wall was completed in the basement and the rooms were painted! The new elevator lift shaft was framed and dry walled. The old bathrooms are gone! It was a busy week. This will be the last Sunday to enter the church through the…
Construction Update Week of December 11
ByAWCCPainting was done, the installation of the rail for the handicap ramp started, tile work began in the bathrooms, new doors were installed, and more electrical work was completed!