Phase I — Building Informational Meeting
Want to know more about the Building Plans? Check out the bulletin board in the lobby to review the plans, and then stay for the meeting after worship on May 8th!!
Goings-on in the AWCC community.
Want to know more about the Building Plans? Check out the bulletin board in the lobby to review the plans, and then stay for the meeting after worship on May 8th!!
Parents of children 12 and under, we will be focusing on the Children’s Service Project this year. You will receive a booklet with stories about refugee children living in Kenya. There are 24 stories to share. Beginning in November, why not read one of those stories as a devotion before dinner and pray for those…
Dry wall was completed in the basement and the rooms were painted! The new elevator lift shaft was framed and dry walled. The old bathrooms are gone! It was a busy week. This will be the last Sunday to enter the church through the…
We made history on Sunday! The vote to proceed with our building program was unanimous and now the journey begins! Thanks to all of you who were able to attend and stand behind this “first” in the history of AWCC. Because we are proceeding, we will have a Groundbreaking Celebration and lunch this Sunday, May 22….
The Cry Room window is in! Concrete work was done downstairs and installation of mechanical (heating and cooling) and electrical systems are underway. New telephone and network cables will be installed soon which is work done “by owner.” Andy Platt and Tim Sophocles are taking the lead on this task. New cabinets for the kitchen…
It’s been a busy week in the basement! The east stairs to the basement were removed, all the walls are removed near those stairs; the lift was moved; ceiling tiles, lights, and carpet was installed in the rooms downstairs, and more painting happened. Please continue to pray for Mark and his crew as they rebuild…
Building Update for the week of July 10-16: Excavation for Phase I construction is complete. Next up is pouring new concrete foundations.To make room for this work, the air conditioning unit and our water supply had to be relocated. Both services have been restored and are available. On Sunday mornings, both building entrances facing the…
Last year a few AWCC folks helped out at Mountair Christian Church on Thanksgiving Day. This church, which is about the same size as Applewood, feeds 400-500 folks a full sit-down turkey dinner. They could use some help again! Ways you can serve: Bring 1, 2, 3 pies for them to serve. They need 75 pies. …
Recent progress by the Building Team towards our Phase 1 building expansion includes: Lee Architects completed a full drawing set which was submitted to Jefferson County for “plan review” on March 18. Jeffco completed their review and issued our building permit on April 1! The team has completed interviews of 4 candidates for general contractor…
The week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…
Our website uses cookies to improve your experience on our site. By using the site, you consent to cookies.
Websites store cookies to enhance functionality and personalise your experience. You can manage your preferences, but blocking some cookies may impact site performance and services.
Essential cookies enable basic functions and are necessary for the proper function of the website.
These cookies are used for managing login functionality on this website.
You can find more information in our Cookie Policy and .