Similar Posts
Construction Update Week of April 1
ByAWCCThere was a lot accomplished again this week! The coils for the heated sidewalks were laid, concrete was poured, stucco work was down outside, more glass was installed in the new entry, and a team moved into the kitchen!
Construction Update August 7
ByAWCCThe week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…
Construction Complete!
ByAWCCJust a few minor finishing touches are left to do! The newly remodeled church and landscaping looks great!
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…
Community Garage Sale
ByAWCCAWCC will be hosting a community garage sale on Saturday, July 6. Anyone interested is welcome to bring their own items to sell and is free to use their own profits at their discretion. Each individual or family is responsible for their own set up and take down, as well as for the sale of…
Building Team Update
ByAWCCRecent progress by the Building Team towards our Phase 1 building expansion includes: Lee Architects completed a full drawing set which was submitted to Jefferson County for “plan review” on March 18. Jeffco completed their review and issued our building permit on April 1! The team has completed interviews of 4 candidates for general contractor…


