Similar Posts
November 27 Construction Update
ByAWCCInspections were completed this week. Installation was installed and drywall was delivered and installed. If you’d like to take a look around the new addition, upstairs and downstairs, it is now safe for you to do that! It’s exciting to see the progress that’s happening. Keep praying for Mark and his team.
Construction Update Week of February 12
ByAWCCDry wall was completed in the basement and the rooms were painted! The new elevator lift shaft was framed and dry walled. The old bathrooms are gone! It was a busy week. This will be the last Sunday to enter the church through the…
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…
Capital Funds Update
ByAWCC$234,900.41 has been given to the Building Fund from 10/1/2010 through 1/1/2012!! That’s more than 100% of the pledged amount of $233,581.11 and 94% of the $250,000 goal. Praise God!
Construction Update Week of February 26
ByAWCCLots happened this week! More painting, more “de-construction” in the northeast corner of the basement (new Preschool room and stairs!), and the opening for the new stairs was made, the sink was installed in the nursery, and more!! Thank you, Just Builders!
Parking Lot Update
ByAWCCThe latest is that the demo will happen the week of 11/26, with the concrete in place by Thurs/Friday. The final grading and paving should happen the following Monday the 3rd.


