Similar Posts
Construction Update Week of March 18
ByAWCCThe floor in the community room was completed, electrical work happened in the preschool room, the lift was worked on, glass was installed on the west side (looks awesome!), and the bricks were removed from the north side in preparation for the new entrance! Construction this week may affect how to enter…
Construction Week of February 5
ByAWCCMore insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!
Building Update July 10
ByAWCCConstruction has begun! The handicap ramp is removed. All the lumber from that is going to be repurposed ! The front sidewalk has been removed and progress is being made! We anticipate having a handicap ramp next Sunday. For safety, please do not enter the construction zone!
Parking Lot Update
ByAWCCThe latest is that the demo will happen the week of 11/26, with the concrete in place by Thurs/Friday. The final grading and paving should happen the following Monday the 3rd.
Construction Update Week of December 4
ByAWCCXcel Energy came out and switched the old service to the new, electrical issues were solved, drywall was installed, skim coating was done, and painting begun! A busy week!
Construction Week of March 11
ByAWCCThe new lobby stairway is installed, the community room floor is down, the new preschool room is framed and insulated, trim work around the outside windows was done, prepping the foundation for the new front steps took place. It’s getting closer to being done!


