Similar Posts
Construction Update Week of February 26
ByAWCCLots happened this week! More painting, more “de-construction” in the northeast corner of the basement (new Preschool room and stairs!), and the opening for the new stairs was made, the sink was installed in the nursery, and more!! Thank you, Just Builders!
November 27 Construction Update
ByAWCCInspections were completed this week. Installation was installed and drywall was delivered and installed. If you’d like to take a look around the new addition, upstairs and downstairs, it is now safe for you to do that! It’s exciting to see the progress that’s happening. Keep praying for Mark and his team.
Building Team Update
ByAWCCWhile we have not yet started construction on Phase I, we are making progress toward that goal. We are working trough details of our contract with Just Builders, checking insurance coverage for both parties, and setting up an escrow account with National Covenant Properties from which construction payments will be made. We don’t have a…
Construction Update Week of June 3
ByAWCCThe glass was installed in the new entryway and landscaping work began!
Construction Week of October 16
ByAWCCMore brick went up on the tower — it’s almost done! Framing continues in the upstairs office area. Work continues downstairs in the kitchen and bath areas. It’s exciting to see all the changes! Thank God for this great adventure!
Construction Update for Week of August 28
ByAWCCConcrete has been poured for the new basement floor in the east expansion. This floor will be under the new restrooms and expanded kitchen. Prior to this, all required plumbing was placed below that floor. Framing is now underway both for this expansion and for the tower. A new structural steel beam is in place…


