Similar Posts
Building Team Update
ByAWCCOur contract has been signed and in effect. Phase I construction will be underway late this week. When you arrive at church next weekend, construction fences will be in place: feel free to look, but don’t go into the construction zone. One inconvenience to the building is that we must cut off the natural gas…
Construction Update — Week of October 2
ByAWCCBrick work continued this week, the handicap ramp was started and more contractors were here doing their work. In this next week, new electrical service will be on Monday, more work on the handicap ramp, HVAC and mechanical contractors will continue their work, and the east wall between the sanctuary and the new addition will…
Construction Update December 18
ByAWCCBathrooms are tiled, electrical work continued, trimming work was done, and kitchen cabinets were installed! Another busy week!
Construction Update Week of December 4
ByAWCCXcel Energy came out and switched the old service to the new, electrical issues were solved, drywall was installed, skim coating was done, and painting begun! A busy week!
Preparing to Build
ByAWCCOver the months and years, stuff has accumulated downstairs! In anticipation of the move, please make sure you have anything of yours that you want to keep that’s in the kitchen or somewhere in the church — and take it home In the next couple of weeks, we will be going through all the storage…
Construction Update Week of September 18
ByAWCCThis past week, framing continued and the nursery wall was taken down and sink taken out. New framing also occurred in the nursery. Some masonry work began this week as well. This week framing the basement walls will continue and the plumbers and mechanical contractors are scheduled to come and begin work!


