Similar Posts
Construction Update Week of January 1, 2012
ByAWCCThe carpeting was installed in the office suite, cabinets were installed in the work room, work continued in the bathrooms downstairs. Staff will be moving into their offices over the next two weeks!
Construction Time Lapse Update
ByAWCCCheck out the latest time lapse of construction at AWCC from July through December! http://vimeo.com/34589050
Construction Update Week of April 29
ByAWCCBrick work began on the front entrance and the pillars, the sidewalk heating system was completed, and work continued in the preschool room!
Construction Update Week of January 30
ByAWCCConstruction in the basement continues — electrical, framing, insulation, finishing the restrooms and more! Please use the new restrooms beginning today!
Building Update — Week of August 14
ByAWCCThe past week the plumbing around the tower was completed and backfilled. You can see the beginnings of the tower out front. Electrical work continues. This next week the new sewer line will be trenched to the street. It will run from the new east addition, around the north side of the building, then west…
Construction Update Week of June 3
ByAWCCThe glass was installed in the new entryway and landscaping work began!


