Similar Posts
Building Team Update — April 24
ByAWCCRecent progress by the Building Team towards our Phase I building expansion includes: Lee Architects released our project for bid to three local contractors on April 21. Bids will be due on May 5. (Pray for bids within our available Building Fund budget!) A team is actively working on concepts for the interior finishes. The…
Parking Lot Goal Reached!
ByAWCCPRAISE GOD And THANK YOU AWCC FAMILY The Parking Lot project is nearly complete and as of June 2nd, sufficient funds have been contributed to provide for the dumpster enclosure and pay off our loan in full! Thanks to all who have worked so hard and contributed generously to make our new parking lot possible….
Construction Update July 28
ByAWCCThe concrete footers for all of the new foundations have been poured and the new foundation walls are underway. On Sunday morning, both building entrances facing the parking lot will be accessible. Please watch your step as you make your way around the construction fence. The interim handicap ramp is in place leading up to…
November 27 Construction Update
ByAWCCInspections were completed this week. Installation was installed and drywall was delivered and installed. If you’d like to take a look around the new addition, upstairs and downstairs, it is now safe for you to do that! It’s exciting to see the progress that’s happening. Keep praying for Mark and his team.
Building Update — Week of August 14
ByAWCCThe past week the plumbing around the tower was completed and backfilled. You can see the beginnings of the tower out front. Electrical work continues. This next week the new sewer line will be trenched to the street. It will run from the new east addition, around the north side of the building, then west…
Construction Update — Week of October 2
ByAWCCBrick work continued this week, the handicap ramp was started and more contractors were here doing their work. In this next week, new electrical service will be on Monday, more work on the handicap ramp, HVAC and mechanical contractors will continue their work, and the east wall between the sanctuary and the new addition will…


