Similar Posts
Construction Update Week of March 25
ByAWCCThere was a lot accomplished this week! Sheet rock was installed in the preschool room and the new lobby and stairway, the cement was poured for part of the new entrance; the new front doors were installed; lots of excavation happened; stucco installation began; and work on the lift continued.
Construction Week of February 5
ByAWCCMore insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!
Construction Update Week of September 11
ByAWCCOur addition on the east end of the church building is taking shape. Framing of the main floor is underway, and will continue next week. On the lower level, demolition of the east basement wall is complete so that the kitchen and mechanical room now open into the new addition. (Sorry, no tours just yet.)…
Construction Time Lapse Update
ByAWCCCheck out the latest time lapse of construction at AWCC from July through December! http://vimeo.com/34589050
Construction Update Week of April 29
ByAWCCBrick work began on the front entrance and the pillars, the sidewalk heating system was completed, and work continued in the preschool room!
Thanksgiving Outreach
ByAWCCLast year a few AWCC folks helped out at Mountair Christian Church on Thanksgiving Day. This church, which is about the same size as Applewood, feeds 400-500 folks a full sit-down turkey dinner. They could use some help again! Ways you can serve: Bring 1, 2, 3 pies for them to serve. They need 75 pies. …


