ByAWCCIt seems that this year has been a little more difficult for people from Arvada Covenant Church to sign up for short-term mission trips. This year ACC still has openings in the following trips before they are full: Honduras – April 13-22 Guatemala – Summer dates to be determined Chihuahua, Mexico – Late June or early July If anyone…
Work Has Started on the Parking Lot
ByAWCCIt’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…
Parking Lot Loan Congregational Meet. & Vote
ByAWCCNational Covenant Properties has approved our loan application for the parking lot. We will need congregational approval of some specific text for that. The meeting will be Sept. 9 after the service, and we will need members to attend for the vote. Heather will work to keep the meeting short so folks can dive into…
Construction Update Week of September 11
ByAWCCOur addition on the east end of the church building is taking shape. Framing of the main floor is underway, and will continue next week. On the lower level, demolition of the east basement wall is complete so that the kitchen and mechanical room now open into the new addition. (Sorry, no tours just yet.)…
Construction Update Week of March 18
ByAWCCThe floor in the community room was completed, electrical work happened in the preschool room, the lift was worked on, glass was installed on the west side (looks awesome!), and the bricks were removed from the north side in preparation for the new entrance! Construction this week may affect how to enter…
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…