Similar Posts
Construction Update Week of September 11
ByAWCCOur addition on the east end of the church building is taking shape. Framing of the main floor is underway, and will continue next week. On the lower level, demolition of the east basement wall is complete so that the kitchen and mechanical room now open into the new addition. (Sorry, no tours just yet.)…
Construction Update Week of February 12
ByAWCCDry wall was completed in the basement and the rooms were painted! The new elevator lift shaft was framed and dry walled. The old bathrooms are gone! It was a busy week. This will be the last Sunday to enter the church through the…
Construction Update July 28
ByAWCCThe concrete footers for all of the new foundations have been poured and the new foundation walls are underway. On Sunday morning, both building entrances facing the parking lot will be accessible. Please watch your step as you make your way around the construction fence. The interim handicap ramp is in place leading up to…
Construction Update Week of December 11
ByAWCCPainting was done, the installation of the rail for the handicap ramp started, tile work began in the bathrooms, new doors were installed, and more electrical work was completed!
Thanksgiving Outreach
ByAWCCLast year a few AWCC folks helped out at Mountair Christian Church on Thanksgiving Day. This church, which is about the same size as Applewood, feeds 400-500 folks a full sit-down turkey dinner. They could use some help again! Ways you can serve: Bring 1, 2, 3 pies for them to serve. They need 75 pies. …
Construction Update Week of February 19
ByAWCCIt’s been a busy week in the basement! The east stairs to the basement were removed, all the walls are removed near those stairs; the lift was moved; ceiling tiles, lights, and carpet was installed in the rooms downstairs, and more painting happened. Please continue to pray for Mark and his crew as they rebuild…


