Construction Update Week of December 4
ByAWCCXcel Energy came out and switched the old service to the new, electrical issues were solved, drywall was installed, skim coating was done, and painting begun! A busy week!
Construction Update Week of April 29
ByAWCCBrick work began on the front entrance and the pillars, the sidewalk heating system was completed, and work continued in the preschool room!
Construction Update August 7
ByAWCCThe week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…
Building Team Update — April 24
ByAWCCRecent progress by the Building Team towards our Phase I building expansion includes: Lee Architects released our project for bid to three local contractors on April 21. Bids will be due on May 5. (Pray for bids within our available Building Fund budget!) A team is actively working on concepts for the interior finishes. The…
Construction Update Week of September 18
ByAWCCThis past week, framing continued and the nursery wall was taken down and sink taken out. New framing also occurred in the nursery. Some masonry work began this week as well. This week framing the basement walls will continue and the plumbers and mechanical contractors are scheduled to come and begin work!