Similar Posts
Construction Week of February 5
ByAWCCMore insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!
Construction Update Week of October 30
ByAWCCThe Cry Room window is in! Concrete work was done downstairs and installation of mechanical (heating and cooling) and electrical systems are underway. New telephone and network cables will be installed soon which is work done “by owner.” Andy Platt and Tim Sophocles are taking the lead on this task. New cabinets for the kitchen…
Construction Week of March 11
ByAWCCThe new lobby stairway is installed, the community room floor is down, the new preschool room is framed and insulated, trim work around the outside windows was done, prepping the foundation for the new front steps took place. It’s getting closer to being done!
Work Has Started on the Parking Lot
ByAWCCIt’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…
Construction Update Week of September 18
ByAWCCThis past week, framing continued and the nursery wall was taken down and sink taken out. New framing also occurred in the nursery. Some masonry work began this week as well. This week framing the basement walls will continue and the plumbers and mechanical contractors are scheduled to come and begin work!
Construction Time Lapse Update
ByAWCCCheck out the latest time lapse of construction at AWCC from July through December! http://vimeo.com/34589050


