Similar Posts
Construction Update Week of October 30
ByAWCCThe Cry Room window is in! Concrete work was done downstairs and installation of mechanical (heating and cooling) and electrical systems are underway. New telephone and network cables will be installed soon which is work done “by owner.” Andy Platt and Tim Sophocles are taking the lead on this task. New cabinets for the kitchen…
Construction Week of October 23
ByAWCCJust Builders is working on reconfiguration of our HVAC (heating and cooling) system and on the vent hoods for the new kitchen. Once these mechanical systems are complete, electricians from Goodman heating systems will be on site to install new electrical circuits. New telephone and network cables will be installed soon which is work done…
Construction Update — Week of September 4
ByAWCCThis past week, Just Builders, began framing the new east addition. This next week they will continue framing and will also break through the old foundation walls into the lower level of the building. This begins the process of merging the new addition with the existing building. Be sure to check out the “color board”…
Mark Your Calendar for AWCC’s 25th Anniversary Celebration: September 7-8
ByAWCCMore info to come!
Construction Update Week of January 23, 2012
ByAWCCLots of demolition has occurred in the basement! Walls have come down, and new walls have been framed. Electrical work continues to happen and the staff is getting settled in their new offices. Please do not use the back stairs. You can also start using the new restrooms next Sunday!
Construction Update August 7
ByAWCCThe week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…


