Similar Posts
Construction Update — Week of September 25
ByAWCCOn the outside of our new addition, you will see windows, waterproofing, and bricks. On the inside, framing in the new addition is well underway. Concrete in the basement floor has been opened up to place required drain lines. Installation of a new furnace unit will be underway soon. The nursery room is being reconfigured…
Global 6K for Water, Saturday, May 4
ByAWCCAt Arvada Covenant Church. There is still time to register online at the following: tinyurl.com/arvada6K. Join the fun for a wonderful cause! If you register by Monday, April 29 at 11:59 pm, you will still get a t-shirt and race bib for the event. Why a 6K? Research has found that about 3.7 miles is…
Construction Update Week of April 1
ByAWCCThere was a lot accomplished again this week! The coils for the heated sidewalks were laid, concrete was poured, stucco work was down outside, more glass was installed in the new entry, and a team moved into the kitchen!
Building Team Update
ByAWCCRecent progress by the Building Team towards our Phase 1 building expansion includes: Lee Architects completed a full drawing set which was submitted to Jefferson County for “plan review” on March 18. Jeffco completed their review and issued our building permit on April 1! The team has completed interviews of 4 candidates for general contractor…
Construction Time Lapse Update
ByAWCCCheck out the latest time lapse of construction at AWCC from July through December! http://vimeo.com/34589050
Construction Update Week of October 30
ByAWCCThe Cry Room window is in! Concrete work was done downstairs and installation of mechanical (heating and cooling) and electrical systems are underway. New telephone and network cables will be installed soon which is work done “by owner.” Andy Platt and Tim Sophocles are taking the lead on this task. New cabinets for the kitchen…


