Similar Posts
November 27 Construction Update
ByAWCCInspections were completed this week. Installation was installed and drywall was delivered and installed. If you’d like to take a look around the new addition, upstairs and downstairs, it is now safe for you to do that! It’s exciting to see the progress that’s happening. Keep praying for Mark and his team.
Construction Update — Week of October 2
ByAWCCBrick work continued this week, the handicap ramp was started and more contractors were here doing their work. In this next week, new electrical service will be on Monday, more work on the handicap ramp, HVAC and mechanical contractors will continue their work, and the east wall between the sanctuary and the new addition will…
Parking Lot Update
ByAWCCThe latest is that the demo will happen the week of 11/26, with the concrete in place by Thurs/Friday. The final grading and paving should happen the following Monday the 3rd.
Construction Update Week of February 26
ByAWCCLots happened this week! More painting, more “de-construction” in the northeast corner of the basement (new Preschool room and stairs!), and the opening for the new stairs was made, the sink was installed in the nursery, and more!! Thank you, Just Builders!
Construction Update Week of November 20
ByAWCCJust Builders is preparing for inspections (electrical, mechanical, plumbing, and structural) in the east addition that are needed before drywall is installed. New telephone and network cables have been installed which was work done “by owner.” Thanks to Andy Platt and Tim Sophocles for taking the lead on this task. The final bricks have been…
Construction Update Week of October 9
ByAWCCWork continues. Brick is going up on the outside, walls are coming down on the inside, Xcel hooked up the gas line, so we now have a furnace, and work continues on the handicap ramp. Mark will let us know when it is safe to look around downstairs, so until then, please stay out of…

