| |

Construction Update December 18

Bathrooms are tiled, electrical work continued, trimming work was done, and kitchen
cabinets were installed! Another busy week!

 

Similar Posts

  • |

    Parking Lot Goal Reached!

    PRAISE GOD And THANK YOU AWCC FAMILY The Parking Lot project is nearly complete and as of June 2nd, sufficient funds have been contributed to provide for the dumpster enclosure and pay off our loan in full!  Thanks to all who have worked so hard and contributed generously to make our new parking lot possible….

  • | |

    Construction Update

    Building Update for the week of July 10-16: Excavation for Phase I construction is complete. Next up is pouring new concrete foundations.To make room for this work, the air conditioning unit and our water supply had to be relocated.  Both services have been restored and are available. On Sunday mornings, both building entrances facing the…

  • |

    Community Garden Work Day

    Can you come help our neighbors put the community garden to bed? Join us Saturday, October 29th (Date Change!) from 9:30 am to noon or so Bring a brunch-type finger food to share, gloves, and a water bottle. Come for all of it or just an hour. Come for any length of time!  

  • | |

    Construction Update August 7

                  The week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…