Similar Posts
Parking Lot Loan Congregational Meet. & Vote
ByAWCCNational Covenant Properties has approved our loan application for the parking lot. We will need congregational approval of some specific text for that. The meeting will be Sept. 9 after the service, and we will need members to attend for the vote. Heather will work to keep the meeting short so folks can dive into…
Building Team Update
ByAWCCOur contract has been signed and in effect. Phase I construction will be underway late this week. When you arrive at church next weekend, construction fences will be in place: feel free to look, but don’t go into the construction zone. One inconvenience to the building is that we must cut off the natural gas…
Work Has Started on the Parking Lot
ByAWCCIt’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…
Construction Update August 7
ByAWCCThe week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…
Construction Week of March 11
ByAWCCThe new lobby stairway is installed, the community room floor is down, the new preschool room is framed and insulated, trim work around the outside windows was done, prepping the foundation for the new front steps took place. It’s getting closer to being done!
Construction Update Week of September 11
ByAWCCOur addition on the east end of the church building is taking shape. Framing of the main floor is underway, and will continue next week. On the lower level, demolition of the east basement wall is complete so that the kitchen and mechanical room now open into the new addition. (Sorry, no tours just yet.)…


