Similar Posts
Construction Update Week of February 12
ByAWCCDry wall was completed in the basement and the rooms were painted! The new elevator lift shaft was framed and dry walled. The old bathrooms are gone! It was a busy week. This will be the last Sunday to enter the church through the…
Construction Week of October 23
ByAWCCJust Builders is working on reconfiguration of our HVAC (heating and cooling) system and on the vent hoods for the new kitchen. Once these mechanical systems are complete, electricians from Goodman heating systems will be on site to install new electrical circuits. New telephone and network cables will be installed soon which is work done…
Parking Lot Update
ByAWCCThe latest is that the demo will happen the week of 11/26, with the concrete in place by Thurs/Friday. The final grading and paving should happen the following Monday the 3rd.
Construction Complete!
ByAWCCJust a few minor finishing touches are left to do! The newly remodeled church and landscaping looks great!
Construction Update Week of March 25
ByAWCCThere was a lot accomplished this week! Sheet rock was installed in the preschool room and the new lobby and stairway, the cement was poured for part of the new entrance; the new front doors were installed; lots of excavation happened; stucco installation began; and work on the lift continued.
Construction Update Week of February 26
ByAWCCLots happened this week! More painting, more “de-construction” in the northeast corner of the basement (new Preschool room and stairs!), and the opening for the new stairs was made, the sink was installed in the nursery, and more!! Thank you, Just Builders!


