Similar Posts
Construction Update Week of November 20
ByAWCCJust Builders is preparing for inspections (electrical, mechanical, plumbing, and structural) in the east addition that are needed before drywall is installed. New telephone and network cables have been installed which was work done “by owner.” Thanks to Andy Platt and Tim Sophocles for taking the lead on this task. The final bricks have been…
Construction Update Week of January 23, 2012
ByAWCCLots of demolition has occurred in the basement! Walls have come down, and new walls have been framed. Electrical work continues to happen and the staff is getting settled in their new offices. Please do not use the back stairs. You can also start using the new restrooms next Sunday!
Construction Update Week of January 1, 2012
ByAWCCThe carpeting was installed in the office suite, cabinets were installed in the work room, work continued in the bathrooms downstairs. Staff will be moving into their offices over the next two weeks!
Building Update — Week of August 14
ByAWCCThe past week the plumbing around the tower was completed and backfilled. You can see the beginnings of the tower out front. Electrical work continues. This next week the new sewer line will be trenched to the street. It will run from the new east addition, around the north side of the building, then west…
Construction Update Week of November 6
ByAWCCMore framing was completed, the masonry work on the tower was finished, work was done on the handicap ramp for heating the ramp and keeping it ice free in the winter, Tim and Andy worked on the phone lines and networking for the church, and the stage doors in the sanctuary were removed and that…
Our 2018/2019 Parking Lot Renovation Capital Campaign is On
ByAWCCTime To Renovate The Parking Lot Our 2018/2019 Capital Campaign is On Commitment Cards in Bulletin & on Lobby Table


