Similar Posts
Construction Update — Week of October 2
ByAWCCBrick work continued this week, the handicap ramp was started and more contractors were here doing their work. In this next week, new electrical service will be on Monday, more work on the handicap ramp, HVAC and mechanical contractors will continue their work, and the east wall between the sanctuary and the new addition will…
Construction Week of February 5
ByAWCCMore insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!
Construction Update Week of November 20
ByAWCCJust Builders is preparing for inspections (electrical, mechanical, plumbing, and structural) in the east addition that are needed before drywall is installed. New telephone and network cables have been installed which was work done “by owner.” Thanks to Andy Platt and Tim Sophocles for taking the lead on this task. The final bricks have been…
Construction Update — Week of September 25
ByAWCCOn the outside of our new addition, you will see windows, waterproofing, and bricks. On the inside, framing in the new addition is well underway. Concrete in the basement floor has been opened up to place required drain lines. Installation of a new furnace unit will be underway soon. The nursery room is being reconfigured…
Construction Update Week of September 11
ByAWCCOur addition on the east end of the church building is taking shape. Framing of the main floor is underway, and will continue next week. On the lower level, demolition of the east basement wall is complete so that the kitchen and mechanical room now open into the new addition. (Sorry, no tours just yet.)…
Construction Update Week of January 30
ByAWCCConstruction in the basement continues — electrical, framing, insulation, finishing the restrooms and more! Please use the new restrooms beginning today!


