Similar Posts
Construction Update Week of April 29
ByAWCCBrick work began on the front entrance and the pillars, the sidewalk heating system was completed, and work continued in the preschool room!
Parking Lot Goal Reached!
ByAWCCPRAISE GOD And THANK YOU AWCC FAMILY The Parking Lot project is nearly complete and as of June 2nd, sufficient funds have been contributed to provide for the dumpster enclosure and pay off our loan in full! Thanks to all who have worked so hard and contributed generously to make our new parking lot possible….
Construction Update Week of March 18
ByAWCCThe floor in the community room was completed, electrical work happened in the preschool room, the lift was worked on, glass was installed on the west side (looks awesome!), and the bricks were removed from the north side in preparation for the new entrance! Construction this week may affect how to enter…
Construction Week of March 11
ByAWCCThe new lobby stairway is installed, the community room floor is down, the new preschool room is framed and insulated, trim work around the outside windows was done, prepping the foundation for the new front steps took place. It’s getting closer to being done!
Work Has Started on the Parking Lot
ByAWCCIt’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…
Construction Week of February 5
ByAWCCMore insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!


