Similar Posts
Construction Update Week of October 9
ByAWCCWork continues. Brick is going up on the outside, walls are coming down on the inside, Xcel hooked up the gas line, so we now have a furnace, and work continues on the handicap ramp. Mark will let us know when it is safe to look around downstairs, so until then, please stay out of…
Construction Update Week of January 1, 2012
ByAWCCThe carpeting was installed in the office suite, cabinets were installed in the work room, work continued in the bathrooms downstairs. Staff will be moving into their offices over the next two weeks!
Construction Update Week of October 30
ByAWCCThe Cry Room window is in! Concrete work was done downstairs and installation of mechanical (heating and cooling) and electrical systems are underway. New telephone and network cables will be installed soon which is work done “by owner.” Andy Platt and Tim Sophocles are taking the lead on this task. New cabinets for the kitchen…
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…
Construction Update Week of March 18
ByAWCCThe floor in the community room was completed, electrical work happened in the preschool room, the lift was worked on, glass was installed on the west side (looks awesome!), and the bricks were removed from the north side in preparation for the new entrance! Construction this week may affect how to enter…
Capital Funds Update
ByAWCC$234,900.41 has been given to the Building Fund from 10/1/2010 through 1/1/2012!! That’s more than 100% of the pledged amount of $233,581.11 and 94% of the $250,000 goal. Praise God!


