| |

Construction during week of August 14-21

The new sewer line is in — and you can get in the front doors to church!  It was a huge job. Electrical work continues and will continue next week. The kitchen is all cleared out. Exciting times ahead!

 

Similar Posts

  • |

    Ground Breaking This Sunday!

    We made history on Sunday! The vote to proceed with our building program was unanimous and now the journey begins! Thanks to all of you who were able to attend and stand behind this “first” in the history of AWCC. Because we are proceeding, we will have a Groundbreaking Celebration and lunch this Sunday, May 22….

  • | |

    Building Team Update

    Recent progress by the Building Team towards our Phase 1 building expansion includes: Lee Architects completed a full drawing set which was submitted to Jefferson County for “plan review” on March 18. Jeffco completed their review and issued our building permit on April 1! The team has completed interviews of 4 candidates for general contractor…

  • | |

    Construction Update Week of February 12

                          Dry wall was completed in the basement and the rooms were painted! The new elevator lift shaft was framed and dry walled. The old bathrooms are gone! It was a busy week. This will be the last Sunday to enter the church through the…

  • | |

    Construction Update Week of October 30

    The Cry Room window is in! Concrete work was done  downstairs and  installation of mechanical (heating and cooling) and electrical systems are underway.  New telephone and network cables will be installed soon which is work done “by owner.”  Andy Platt and Tim Sophocles are taking the lead on this task.  New cabinets for the kitchen…

  • |

    Parking Lot Goal Reached!

    PRAISE GOD And THANK YOU AWCC FAMILY The Parking Lot project is nearly complete and as of June 2nd, sufficient funds have been contributed to provide for the dumpster enclosure and pay off our loan in full!  Thanks to all who have worked so hard and contributed generously to make our new parking lot possible….

  • | |

    Construction Update

    Building Update for the week of July 10-16: Excavation for Phase I construction is complete. Next up is pouring new concrete foundations.To make room for this work, the air conditioning unit and our water supply had to be relocated.  Both services have been restored and are available. On Sunday mornings, both building entrances facing the…