Similar Posts
Work Has Started on the Parking Lot
ByAWCCIt’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…
Construction Week of October 16
ByAWCCMore brick went up on the tower — it’s almost done! Framing continues in the upstairs office area. Work continues downstairs in the kitchen and bath areas. It’s exciting to see all the changes! Thank God for this great adventure!
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…
Construction Update — Week of October 2
ByAWCCBrick work continued this week, the handicap ramp was started and more contractors were here doing their work. In this next week, new electrical service will be on Monday, more work on the handicap ramp, HVAC and mechanical contractors will continue their work, and the east wall between the sanctuary and the new addition will…
Construction Update Week of January 1, 2012
ByAWCCThe carpeting was installed in the office suite, cabinets were installed in the work room, work continued in the bathrooms downstairs. Staff will be moving into their offices over the next two weeks!
Construction Update Week of April 29
ByAWCCBrick work began on the front entrance and the pillars, the sidewalk heating system was completed, and work continued in the preschool room!



