Similar Posts
Work Has Started on the Parking Lot
ByAWCCIt’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…
Capital Funds Update
ByAWCC$234,900.41 has been given to the Building Fund from 10/1/2010 through 1/1/2012!! That’s more than 100% of the pledged amount of $233,581.11 and 94% of the $250,000 goal. Praise God!
Construction Update for Week of August 28
ByAWCCConcrete has been poured for the new basement floor in the east expansion. This floor will be under the new restrooms and expanded kitchen. Prior to this, all required plumbing was placed below that floor. Framing is now underway both for this expansion and for the tower. A new structural steel beam is in place…
Construction Update Week of March 25
ByAWCCThere was a lot accomplished this week! Sheet rock was installed in the preschool room and the new lobby and stairway, the cement was poured for part of the new entrance; the new front doors were installed; lots of excavation happened; stucco installation began; and work on the lift continued.
Construction Update Week of June 24
ByAWCCLandscaping was done last week, and finishing touches were worked on inside the building! Construction is almost complete!
Construction Update Week of October 9
ByAWCCWork continues. Brick is going up on the outside, walls are coming down on the inside, Xcel hooked up the gas line, so we now have a furnace, and work continues on the handicap ramp. Mark will let us know when it is safe to look around downstairs, so until then, please stay out of…



