Similar Posts
Construction Update Week of November 6
ByAWCCMore framing was completed, the masonry work on the tower was finished, work was done on the handicap ramp for heating the ramp and keeping it ice free in the winter, Tim and Andy worked on the phone lines and networking for the church, and the stage doors in the sanctuary were removed and that…
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…
November 27 Construction Update
ByAWCCInspections were completed this week. Installation was installed and drywall was delivered and installed. If you’d like to take a look around the new addition, upstairs and downstairs, it is now safe for you to do that! It’s exciting to see the progress that’s happening. Keep praying for Mark and his team.
Short-Term Mission Opportunities
ByAWCCIt seems that this year has been a little more difficult for people from Arvada Covenant Church to sign up for short-term mission trips. This year ACC still has openings in the following trips before they are full: Honduras – April 13-22 Guatemala – Summer dates to be determined Chihuahua, Mexico – Late June or early July If anyone…
Building Update July 10
ByAWCCConstruction has begun! The handicap ramp is removed. All the lumber from that is going to be repurposed ! The front sidewalk has been removed and progress is being made! We anticipate having a handicap ramp next Sunday. For safety, please do not enter the construction zone!
Construction Update Week of December 4
ByAWCCXcel Energy came out and switched the old service to the new, electrical issues were solved, drywall was installed, skim coating was done, and painting begun! A busy week!



