Similar Posts
Construction Update
ByAWCCBuilding Update for the week of July 10-16: Excavation for Phase I construction is complete. Next up is pouring new concrete foundations.To make room for this work, the air conditioning unit and our water supply had to be relocated. Both services have been restored and are available. On Sunday mornings, both building entrances facing the…
Construction Update — Week of September 4
ByAWCCThis past week, Just Builders, began framing the new east addition. This next week they will continue framing and will also break through the old foundation walls into the lower level of the building. This begins the process of merging the new addition with the existing building. Be sure to check out the “color board”…
Construction Update for Week of August 28
ByAWCCConcrete has been poured for the new basement floor in the east expansion. This floor will be under the new restrooms and expanded kitchen. Prior to this, all required plumbing was placed below that floor. Framing is now underway both for this expansion and for the tower. A new structural steel beam is in place…
Construction Week of October 23
ByAWCCJust Builders is working on reconfiguration of our HVAC (heating and cooling) system and on the vent hoods for the new kitchen. Once these mechanical systems are complete, electricians from Goodman heating systems will be on site to install new electrical circuits. New telephone and network cables will be installed soon which is work done…
Construction Update Week of May 13
ByAWCCThe Preschool Room looks awesome, the brick work looks great. Just waiting for the manufacturer to deliver the glass for the entry way and some inspections. It’s getting close to being completed!
Construction Update Week of December 4
ByAWCCXcel Energy came out and switched the old service to the new, electrical issues were solved, drywall was installed, skim coating was done, and painting begun! A busy week!


