| |

Capital Funds Update

$234,900.41 has been given to the Building Fund from  10/1/2010 through 1/1/2012!!   That’s more than 100% of the pledged amount of $233,581.11 and 94% of the $250,000 goal.  Praise God!

 

Similar Posts

  • |

    Building Team Update

    Our contract has been signed and in effect.  Phase I  construction will be underway late this week. When you arrive at church next weekend, construction fences will be in place:  feel free to look, but don’t go into the construction zone.  One inconvenience to the building is that we must cut off the natural gas…

  • | |

    Construction Update Week of September 11

    Our addition on the east end of the church building is taking shape. Framing of the  main floor is  underway, and  will continue  next week. On the lower level, demolition of the east basement wall is complete so that the kitchen and mechanical room now open into the new  addition.  (Sorry, no tours just yet.)…

  • | |

    Basement Construction

    Beginning next Sunday, kids will remain in the service for the whole time. They will not be dismissed downstairs to KidsCrossing! The only part of the basement that will be accessible  during this next phase will be the bathrooms! We need your help in making this work on Sunday mornings! If you do not have…

  • | |

    Construction Update — Week of September 4

    This past week, Just Builders, began framing the new east addition.  This next week they will continue framing and will also break through the old foundation walls into the lower level of the building.  This begins the process of merging the new addition with the existing building. Be sure to check out the “color board”…

  • |

    Building Update July 10

    Construction has begun! The handicap ramp is removed. All the lumber from that is going to be repurposed ! The front sidewalk has been removed and progress is being made!  We anticipate having a handicap ramp next Sunday. For safety, please do not enter the construction zone!    

  • |

    Work Has Started on the Parking Lot

    It’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…