| |

Construction Update for Week of August 28

Concrete has been poured for the new basement floor in the east expansion.  This floor will be under the new restrooms and expanded kitchen.  Prior to this, all required
plumbing was placed below that floor.  Framing is now underway both for this expansion and for the tower.  A new structural steel beam is in place which will allow us to break through the old basement wall into the new expansion in the basement.  The Interior Design Team has completed a “color board” which displays their recommendations for finishes including paint colors, floor coverings, cabinets, countertops, and restroom floor tiles.  Look for the color board in the lobby.

 

Similar Posts

  • |

    Building Team Update

    Our contract has been signed and in effect.  Phase I  construction will be underway late this week. When you arrive at church next weekend, construction fences will be in place:  feel free to look, but don’t go into the construction zone.  One inconvenience to the building is that we must cut off the natural gas…

  • |

    Work Has Started on the Parking Lot

    It’s great to get started. All the conduit for light poles are in place! I did meet with the paving contractor Thursday and was a bit disappointed with their schedule but they will make it work. Concrete work is to commence the 2nd week of November and removal and replacement of the asphalt the following…

  • | |

    Building Team Update

    Recent progress by the Building Team towards our Phase 1 building expansion includes: Lee Architects completed a full drawing set which was submitted to Jefferson County for “plan review” on March 18. Jeffco completed their review and issued our building permit on April 1! The team has completed interviews of 4 candidates for general contractor…

  • |

    We Need More Room!

    God has been working and growing our church family. After many discussions, much prayer and discovering what our “DNA” is as a church, we realized that we are a family and want to worship in the same building, which means that instead of building a separate building for the kids and a separate place for…

  • |

    Thanksgiving Outreach

    Last year a few AWCC folks helped out at Mountair Christian Church on Thanksgiving Day. This church, which is about the same size as Applewood, feeds 400-500 folks a full sit-down turkey dinner. They could use some help again! Ways you can serve: Bring 1, 2, 3 pies for them to serve. They need 75 pies. …