Similar Posts
Construction Update Week of May 27
ByAWCCWe are on the homestretch with construction activities for Phase I! The 5th classroom room in the basement is now done and almost occupied. (Some ceiling tiles are purposely on hold pending a final inspection.) Carpeting in the lift room and northwest stairway will be done by Sunday, June 10. The new main entrance is…
Construction Week of October 16
ByAWCCMore brick went up on the tower — it’s almost done! Framing continues in the upstairs office area. Work continues downstairs in the kitchen and bath areas. It’s exciting to see all the changes! Thank God for this great adventure!
Parking Lot Loan Congregational Meet. & Vote
ByAWCCNational Covenant Properties has approved our loan application for the parking lot. We will need congregational approval of some specific text for that. The meeting will be Sept. 9 after the service, and we will need members to attend for the vote. Heather will work to keep the meeting short so folks can dive into…
Construction Update Week of November 6
ByAWCCMore framing was completed, the masonry work on the tower was finished, work was done on the handicap ramp for heating the ramp and keeping it ice free in the winter, Tim and Andy worked on the phone lines and networking for the church, and the stage doors in the sanctuary were removed and that…
Construction Update Week of January 1, 2012
ByAWCCThe carpeting was installed in the office suite, cabinets were installed in the work room, work continued in the bathrooms downstairs. Staff will be moving into their offices over the next two weeks!
Parking Lot Goal Reached!
ByAWCCPRAISE GOD And THANK YOU AWCC FAMILY The Parking Lot project is nearly complete and as of June 2nd, sufficient funds have been contributed to provide for the dumpster enclosure and pay off our loan in full! Thanks to all who have worked so hard and contributed generously to make our new parking lot possible….



