Similar Posts
Construction Week of March 11
ByAWCCThe new lobby stairway is installed, the community room floor is down, the new preschool room is framed and insulated, trim work around the outside windows was done, prepping the foundation for the new front steps took place. It’s getting closer to being done!
Construction Update — Week of September 4
ByAWCCThis past week, Just Builders, began framing the new east addition. This next week they will continue framing and will also break through the old foundation walls into the lower level of the building. This begins the process of merging the new addition with the existing building. Be sure to check out the “color board”…
Construction Update August 7
ByAWCCThe week of August 8, the new sewer line will be trenched. It will run from the new east addition, around the north side of the building, then west to Zinnia Street. All access to the building direct from the parking lot will be cut off during the…
Building Team Update — April 24
ByAWCCRecent progress by the Building Team towards our Phase I building expansion includes: Lee Architects released our project for bid to three local contractors on April 21. Bids will be due on May 5. (Pray for bids within our available Building Fund budget!) A team is actively working on concepts for the interior finishes. The…
Construction Week of February 5
ByAWCCMore insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!
Construction Time Lapse Update
ByAWCCCheck out the latest time lapse of construction at AWCC from July through December! http://vimeo.com/34589050
