The forms for the steps were created and concrete was poured! Work continued in the new Preschool room.
There was a lot accomplished again this week! The coils for the heated sidewalks were laid, concrete was poured, stucco work was down outside, more glass was installed in the new entry, and a team moved into the kitchen!…
There was a lot accomplished this week! Sheet rock was installed in the preschool room and the new lobby and stairway, the cement was poured for part of the new entrance; the new front doors were installed; lots of…
The floor in the community room was completed, electrical work happened in the preschool room, the lift was worked on, glass was installed on the west side (looks awesome!), and the bricks were removed from the…
The new lobby stairway is installed, the community room floor is down, the new preschool room is framed and insulated, trim work around the outside windows was done, prepping the foundation for the new front steps took place. It’s…
Lots happened this week! More painting, more “de-construction” in the northeast corner of the basement (new Preschool room and stairs!), and the opening for the new stairs was made, the sink was installed in the nursery, and more!! Thank…
It’s been a busy week in the basement! The east stairs to the basement were removed, all the walls are removed near those stairs; the lift was moved; ceiling tiles, lights, and carpet was installed in the rooms downstairs,…
Dry wall was completed in the basement and the rooms were painted! The new elevator lift shaft was framed and dry walled. The old bathrooms are gone! It…
More insulation and dry walling happened in the basement this week. It’s looking great! Continue to keep Mark, his workers and Just Builders in your prayers!
Construction in the basement continues — electrical, framing, insulation, finishing the restrooms and more! Please use the new restrooms beginning today!